Further Temple Progress

Just in the last couple of days or so, a lot has happened on the temple news front. Here's my updated progress report, as of yesterday. Enjoy, and let me know what you think!

Temple Construction Progress Report (current as of 9/23/16)
Current Temple Status: 152 operating; scheduled for dedication; 11 under construction; 3 undergoing renovation; 11 announced (As many as 3 groundbreaking announcements may be made soon).

Dedication scheduled:
153. Fort Collins Colorado Temple: Preparing for dedication, scheduled on Sunday October 16, 2016.
154. Star Valley Wyoming Temple: Open house tours underway through Saturday October 8; dedication scheduled on Sunday October 30, 2016.
155. Hartford Connecticut Temple: Accepting reservations for public open house scheduled September 30-October 22; dedication scheduled on Sunday November 20, 2016.

Under Construction:
156. Paris France Temple: Stained glass installation underway; entrance landscaping progressing; completion anticipated sometime in early-to-mid 2017.
157. Meridian Idaho Temple: Concrete slab in place for monument sign; planting trees and bushes; completion anticipated sometime in late 2017.
158. Cedar City Utah Temple: Angel Moroni placed on September 15, 2016; completion anticipated sometime in late 2017.
159. Tucson Arizona Temple: Pouring concrete parking lot; interior work underway; completion anticipated sometime in late 2017.
160. Rome Italy Temple: Interior work underway including some material replacement and rework; completion anticipated sometime in the first half of 2018.
161. Concepcion Chile Temple: Pouring walls for base of tower; preparing to attach exterior panels; completion anticipated sometime in 2018.
162. Kinshasa Democratic Republic of the Congo Temple: Foundation poured and backfilled; pouring interior footings; completion anticipated sometime in 2018.
163. Durban South Africa Temple: Excavation for foundation underway; preparing the parking area; completion anticipated sometime in 2018.
164. Barranquilla Colombia Temple: Foundation walls going up; completion anticipated sometime in 2019.
165.  Fortaleza Brazil Temple: Forms and rebar set in anticipation of pouring foundation walls; completion anticipated sometime in 2019.
166. Lisbon Portugal Temple: Site clearing underway; completion anticipated sometime in 2019.

Undergoing Renovation:
8. Idaho Falls Idaho Temple: Closed for renovation; finish work underway; resurfacing and restriping parking lot; rededication anticipated sometime during the first quarter of 2017.
20. Jordan River Utah Temple: Closed for renovation; rededication anticipated sometime in late 2017.
41. Frankfurt Germany Temple: Closed for renovation; rededication anticipated sometime in 2018.



Announced:
167. Arequipa Peru Temple: No groundbreaking date set, however, construction is pending, and, according to the contractor for the project, that construction anticipated to begin sometime during late 2016.
168. Rio de Janeiro Brazil Temple: No groundbreaking set. However, construction anticipated to begin late 2016 or early 2017.
169. Winnipeg Manitoba Temple: Approval and permitting phase; temple fireside held September 11, 2016; groundbreaking anticipated for early 2017.
170. Urdaneta Philippines Temple: Planning and approval phase; awaiting official site announcement.
171. Port-au-Prince Haiti Temple: Planning and approval phase; awaiting official site announcement.
172. Bangkok Thailand Temple: Planning and approval phase; awaiting official site announcement.
173. Abidjan Ivory Coast Temple: Planning phase; awaiting official site announcement.
174. Quito Ecuador Temple: Planning phase; awaiting official site announcement.
175. Harare Zimbabwe Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil Temple: Planning phase; awaiting official site announcement.
177. Lima Peru Los Olivos Temple: Planning phase; awaiting official site announcement.

Key:
Bolded numbers and text denote temples whose numbers already exists (for renovations), or is certain due to a scheduled dedication, as well as information that is certain, such as dedication or groundbreaking dates.
Italicized numbers and text denote temples whose numbers may change based on the order in which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote temples whose numbers may change based on progress towards planning, approval, and groundbreaking.
Red text denotes changes from the last posted temple progress update.

Thursday, September 22, 2016

Major temple construction progress

Rick Satterfield has made major changes in the way temples are listed for completion. He has moved Durban and Kinshasa up to be completed in 2018. He has moved Barranquilla and Fortaleza down to be completed in 2019. To give you an idea of what has changed with the construction status of temples, I am posting my progress report which is current as of today. Please also note that the open house for the Star Valley Wyoming temple starts tomorrow. Enjoy, and let me know what you think.

Temple Construction Progress Report (current as of 9/22/16)
Current Temple Status: 152 operating; scheduled for dedication; 11 under construction; 3 undergoing renovation; 11 announced (As many as 3 groundbreaking announcements may be made soon).

Dedication scheduled:
153. Fort Collins Colorado Temple: Preparing for dedication, scheduled on Sunday October 16, 2016.
154. Star Valley Wyoming Temple: Accepting reservations for public open house, scheduled September 23-October 8; dedication scheduled on Sunday October 30, 2016.
155. Hartford Connecticut Temple: Accepting reservations for public open house scheduled September 30-October 22; dedication scheduled on Sunday November 20, 2016.

Under Construction:
156. Paris France Temple: Stained glass installation underway; entrance landscaping progressing; completion anticipated sometime in early-to-mid 2017.
157. Meridian Idaho Temple: Concrete slab in place for monument sign; planting trees and bushes; completion anticipated sometime in late 2017.
158. Cedar City Utah Temple: Angel Moroni placed on September 15, 2016; completion anticipated sometime in late 2017.
159. Tucson Arizona Temple: Retaining walls in place; pouring concrete parking lot; completion anticipated sometime in late 2017.
160. Rome Italy Temple: Interior work underway including some material replacement and rework; completion anticipated sometime in the first half of 2018.
161. Concepcion Chile Temple: Pouring walls for base of tower; preparing to attach exterior panels; completion anticipated sometime in 2018.
162. Kinshasa Democratic Republic of the Congo Temple: Foundation poured and backfilled; pouring interior footings; completion anticipated sometime in 2018.
163. Durban South Africa Temple: Excavation for foundation underway; preparing the parking area; completion anticipated sometime in 2018.
164. Barranquilla Colombia Temple: Foundation walls going up; Elder Renlund visits temple site in August; completion anticipated sometime in 2019.
165.  Fortaleza Brazil Temple: Forms and rebar set in anticipation of pouring foundation walls; completion anticipated sometime in 2019.
166. Lisbon Portugal Temple: Site clearing underway; completion anticipated sometime in 2019.

Undergoing Renovation:
8. Idaho Falls Idaho Temple: Closed for renovation; finish work underway; resurfacing and restriping parking lot; rededication anticipated sometime during the first quarter of 2017.
20. Jordan River Utah Temple: Closed for renovation; rededication anticipated sometime in late 2017.
41. Frankfurt Germany Temple: Closed for renovation; rededication anticipated sometime in 2018.

Announced:
167. Arequipa Peru Temple: No groundbreaking date set, however, construction is pending, and, according to the contractor for the project, that construction anticipated to begin sometime during late 2016.
168. Rio de Janeiro Brazil Temple: No groundbreaking set. However, construction anticipated to begin late 2016 or early 2017.
169. Winnipeg Manitoba Temple: Approval and permitting phase; temple fireside held September 11, 2016; groundbreaking anticipated for early 2017.
170. Urdaneta Philippines Temple: Planning and approval phase; awaiting official site announcement.
171. Port-au-Prince Haiti Temple: Planning and approval phase; awaiting official site announcement.
172. Bangkok Thailand Temple: Planning and approval phase; awaiting official site announcement.
173. Abidjan Ivory Coast Temple: Planning phase; awaiting official site announcement.
174. Quito Ecuador Temple: Planning phase; awaiting official site announcement.
175. Harare Zimbabwe Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil Temple: Planning phase; awaiting official site announcement.
177. Lima Peru Los Olivos Temple: Planning phase; awaiting official site announcement.

Key:
Bolded numbers and text denote temples whose numbers already exists (for renovations), or is certain due to a scheduled dedication, as well as information that is certain, such as dedication or groundbreaking dates.
Italicized numbers and text denote temples whose numbers may change based on the order in which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote temples whose numbers may change based on progress towards planning, approval, and groundbreaking.
Red text denotes changes from the last posted temple progress update.

Wednesday, September 21, 2016

Changes in wording and order for temple progress

Hello, all! Though there has been no notable progress in temple construction since I posted my list yesterday, I have made several stylistic edits.

The first involved change the word estimated to the word anticipated in terms of completion or groundbreaking dates.

The second and by far the biggest change was moving up the completion date for the Barranquilla Colombia temple to between late 2018 and early 2019. I also put it ahead of the Kinshasa temple. Though that change is not and may not ever be on Brother Satterfield's website, I felt it was warranted. In my mind, the fact that foundation walls are going up in Barranquilla puts it ahead of Kinshasa, which is just having its foundation poured. He and you guys may disagree with me on this. Just let me know what you think.

Because of the changes, both slight and major, I have felt it appropriate to repost my list of temple progress. Enjoy!

Temple Construction Progress Report (current as of 9/21/16)
Current Temple Status: 152 operating;  scheduled for dedication;
11  under construction; 3 undergoing renovation; As many as 3 groundbreaking announcements may be made soon).

Dedication scheduled:
153. Fort Collins Colorado Temple: Preparing for dedication, scheduled on Sunday October 16, 2016.
154. Star Valley Wyoming Temple: Accepting reservations for public open house, scheduled September 23-October 8; dedication scheduled on Sunday October 30, 2016.
155. Hartford Connecticut Temple: Accepting reservations for public open house scheduled September 30-October 22; dedication scheduled on Sunday November 20, 2016.

Under Construction:
156. Paris France Temple: Stained glass installation underway; entrance landscaping progressing; completion anticipated sometime in early-to-mid 2017.
157. Meridian Idaho Temple: Concrete slab in place for monument sign; planting trees and bushes; completion anticipated sometime in late 2017.
158. Cedar City Utah Temple: Angel Moroni placed on September 15, 2016; completion anticipated sometime in late 2017.
159. Tucson Arizona Temple: Retaining walls in place; pouring concrete parking lot; completion anticipated sometime in late 2017.
160. Rome Italy Temple: Interior work underway including some material replacement and rework; completion anticipated sometime in the first half of 2018.
161. Concepcion Chile Temple: Pouring walls for base of tower; preparing to attach exterior panels; completion anticipated sometime in late 2018.
162. Barranquilla Colombia Temple: Foundation walls going up; Elder Renlund visits temple site in August; completion anticipated sometime between late 2018 and early 2019.
163. Kinshasa Democratic Republic of the Congo Temple: Foundation poured and backfilled; completion anticipated sometime between late 2018 and early 2019.
164.  Fortaleza Brazil Temple: Forms and rebar set in anticipation of pouring foundation walls; completion anticipated sometime in 2019.
165. Durban South Africa Temple: Excavation for foundation underway; preparing the parking area; completion anticipated sometime in 2019.
166. Lisbon Portugal Temple: Site clearing underway; completion anticipated sometime in 2019.

Undergoing Renovation:
8. Idaho Falls Idaho Temple: Closed for renovation; finish work underway; resurfacing and restriping parking lot; rededication anticipated sometime during the first quarter of 2017.
20. Jordan River Utah Temple: Closed for renovation; rededication anticipated sometime in late 2017.
41. Frankfurt Germany Temple: Closed for renovation; rededication anticipated sometime in 2018.

Announced:
167. Arequipa Peru Temple: No groundbreaking date set, however, construction is pending, and, according to the contractor for the project, that construction anticipated to begin sometime during late 2016.
168. Rio de Janeiro Brazil Temple: No groundbreaking set. However, construction anticipated to begin late 2016 or early 2017.
169. Winnipeg Manitoba Temple: Approval and permitting phase; temple fireside held September 11, 2016; groundbreaking anticipated for early 2017.
170. Urdaneta Philippines Temple: Planning and approval phase; awaiting official site announcement.
171. Port-au-Prince Haiti Temple: Planning and approval phase; awaiting official site announcement.
172. Bangkok Thailand Temple: Planning and approval phase; awaiting official site announcement.
173. Abidjan Ivory Coast Temple: Planning phase; awaiting official site announcement.
174. Quito Ecuador Temple: Planning phase; awaiting official site announcement.
175. Harare Zimbabwe Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil Temple: Planning phase; awaiting official site announcement.
177. Lima Peru Los Olivos Temple: Planning phase; awaiting official site announcement.

Key:
Bolded numbers and text denote temples whose numbers already exists (for renovations), or is certain due to a scheduled dedication, as well as information that is certain, such as dedication or groundbreaking dates.
Italicized numbers and text denote temples whose numbers may change based on the order in which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote temples whose numbers may change based on progress towards planning, approval, and groundbreaking.
Red text denotes changes from the last posted temple progress update

Changes in Editorship and Adivsership of the Church Magazines

There have been changes in the editors and advisers of the Church Magazines. This is according to the PDF version of the October Ensign. The changes are primarily the result of James B. Martino, assistant editor, and Craig A. Cardon, an adviser, receiving assignments in international area presidencies. The changes are as follows:

September 2016:
Editor: Joseph W. Sitati
Assistant Editors: James B. Martino, Carol F. McConkie
Advisers: Brian K. Ashton, Randall K. Bennett, Jean B. Bingham, Craig A. Cardon, Christoffel Golden, Douglas D. Holmes, Larry R. Lawrence, Carole M. Stephens

October 2016:
Editor: Joseph W. Sitati
Assistant Editors: Randall K. Bennett, Carol F. McConkie
Advisers: Brian K. Ashton, Jean B. Bingham, Legrand R. Curtis Jr., Christoffel Golden, Douglas D. Holmes, Erich W. Kopischke, Larry R. Lawrence, Carole M. Stephens

Released as Assistant Editor: James B. Martino:
Called as Assistant Editor: Randall K. Bennett
Released as Advisers: Randall K. Bennett, Craig A. Cardon
Called as Advisers: LeGrand R. Curtis, Jr., Erich W. Kopischke


Sunday, September 18, 2016

Important temple strides

Hello, all! Hope you are well. I wanted to post today with news that the Philadelpha Pennsylvania Temple was dedicated today, one day after the most recent anniversary of the signing of the Constitution. As I expected, President Eyring presided at that event. He was accompanied by Elder D. Todd Christofferson of the Quorum of the Twelve Apostles and Elder Gerrit W. Gong of the Presidency of the Seventy, who has supervisory responsibilities for the North America Northeast Area and Elders Larry Y. Wilson of the Seventy (who serves as the temple department executive director) and Anthony D. Perkins (who may be an assistant executive director for the temple department).

Additionally, trees and bushes are being placed on the grounds of the Meridian Idaho temple.

Here is an updated list of Church temple progress:

Temple Construction Progress Report (current as of 9/18/16)
Current Temple Status: 152 operating; 
3 scheduled for dedication; 11 under construction; 3 undergoing renovation; 11 announced (As many as 3 groundbreaking announcements may be made soon).

Dedication scheduled:
153. Fort Collins Colorado Temple: Preparing for dedication, scheduled on Sunday October 16, 2016.
154. Star Valley Wyoming Temple: Accepting reservations for public open house, scheduled September 23-October 8; dedication scheduled on Sunday October 30, 2016.
155. Hartford Connecticut Temple: Accepting reservations for public open house scheduled September 30-October 22; dedication scheduled on Sunday November 20, 2016.

Under Construction:
156. Paris France Temple: Stained glass installation underway; entrance landscaping progressing; completion estimated sometime in early-to-mid 2017.
157. Meridian Idaho Temple: Concrete slab in place for monument sign; planting trees and bushes; completion estimated sometime in late 2017.
158. Cedar City Utah Temple: Angel Moroni placed on September 15, 2016; completion estimated sometime in late 2017.
159. Tucson Arizona Temple: Retaining walls in place; pouring concrete parking lot; completion estimated sometime in late 2017.
160. Rome Italy Temple: Interior work underway including some material replacement and rework; completion estimated sometime in the first half of 2018.
161. Concepcion Chile Temple: Pouring walls for base of tower; preparing to attach exterior panels; completion estimated sometime in late 2018.
162. Kinshasa Democratic Republic of the Congo Temple: Foundation poured and backfilled; completion estimated sometime between late 2018 and early 2019.
163. Barranquilla Colombia Temple: Foundation walls going up; Elder Renlund visits temple site in August; completion estimated sometime in 2019.
164.  Fortaleza Brazil Temple: Forms and rebar set in anticipation of pouring foundation walls; completion estimated sometime in 2019.
165. Durban South Africa Temple: Sinking piles for foundation and terracing soil; completion estimated sometime in 2019.
166. Lisbon Portugal Temple: Site clearing underway; completion estimated sometime in 2019.

Undergoing Renovation:
8. Idaho Falls Idaho Temple: Closed for renovation; finish work underway; resurfacing and restriping parking lot; rededication estimated sometime during the first quarter of 2017.
20. Jordan River Utah Temple: Closed for renovation; rededication estimated sometime in late 2017.
41. Frankfurt Germany Temple: Closed for renovation; rededication estimated sometime in 2018.
Announced:
167. Arequipa Peru Temple: No groundbreaking date set, however, construction is pending, and, according to the contractor for the project, that construction may begin later this year.
168. Rio de Janeiro Brazil Temple: No groundbreaking set. However, construction anticipated to begin late this year or early next year.
169. Winnipeg Manitoba Temple: Approval and permitting phase; temple fireside held September 11, 2016; groundbreaking anticipated for early 2017.
170. Urdaneta Philippines Temple: Planning and approval phase; awaiting official site announcement.
171. Port-au-Prince Haiti Temple: Planning and approval phase; awaiting official site announcement.
172. Bangkok Thailand Temple: Planning and approval phase; awaiting official site announcement.
173. Abidjan Ivory Coast Temple: Planning phase; awaiting official site announcement.
174. Quito Ecuador Temple: Planning phase; awaiting official site announcement.
175. Harare Zimbabwe Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil Temple: Planning phase; awaiting official site announcement.
177. Lima Peru Los Olivos Temple: Planning phase; awaiting official site announcement.

Key:
Bolded numbers and text denote temples whose numbers already exists (for renovations), or is certain due to a scheduled dedication, as well as information that is certain, such as dedication or groundbreaking dates.
Italicized numbers and text denote temples whose numbers may change based on the order in which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote temples whose numbers may change based on progress towards planning, approval, and groundbreaking.

Red text denotes changes from the last posted temple progress update/