With that noted, I don't believe I have mentioned this before, but the Facebook page for the Oakland California Temple (the 13th Church temple dedicated, which happened over 50 years ago, in 1964, well into the presidency of 9th Church President David O. McKay) reports that the temple will close in February of next year for extensive renovation that will make it necessary for the temple to have another open house and dedication. The renovation, which will last a minimum of a year, is appearing for the first time on this report.
This report will hopefully be followed up very shortly by yet another revision for my estimates of the timeline by which future temple-related events might be scheduled and subsequently take place. It all depends on how fast I am able to get that done. That said, for what it's worth, you will find my updated progress report below. I welcome any and all feedback. Thanks so much for taking time to read (and comment, if you feel so inclined). I look forward to being able to report on all temple-related developments as I might hear of them. Thanks again.
Temple Construction Progress Update
(current as of 2/19/17)
Current Temple Status: 155 operating; 4 scheduled
for dedication; 8 under construction; 2 groundbreakings scheduled; 1 scheduled
for rededication; 2 undergoing renovation; 1 renovation scheduled; 8 announced. NOTE:
In addition to the two groundbreakings already scheduled this year, the chances
are very good that we will see several others also have a groundbreaking in
2017.
Dedication scheduled:
156. Paris France
Temple: Accepting reservations for public open house
beginning Monday February 27; dedication scheduled for Sunday
May 21, 2017.
157. Tucson
Arizona Temple: Desert landscaping progressing; exterior architectural details
gilded; installing interior art glass and millwork; dedication scheduled for Sunday August 13, 2017.
158. Meridian
Idaho Temple: Interior painting and millwork underway; dedication
scheduled for Sunday November 19, 2017.
159. Cedar
City Utah Temple: Installing art glass windows; hanging drywall on interior;
dedication scheduled for Sunday December
10, 2017.
Under Construction:
160. Rome Italy Temple:
Interior work progressing; completion anticipated
sometime between early and mid-2018.
161. Kinshasa
Democratic Republic of the Congo Temple: Applying waterproofing membrane
to exterior walls; setting rebar; roughing in plumbing; completion
anticipated sometime between early and mid-2018.
162. Barranquilla
Colombia Temple: Concrete walls poured for steeple; attaching waterproofing
membrane to exterior walls; completion anticipated sometime during mid-2018.
163. Concepcion Chile
Temple: Exterior cladding going up on north wall; framing the interior walls; completion
anticipated sometime during mid-to-late 2018.
164. Durban South Africa
Temple: Backfilling foundation; preparing for ground floor; missionary housing
walls poured; completion anticipated sometime during mid-to-late 2018.
165. Fortaleza Brazil
Temple: Parapet poured; some scaffolding coming down; preparing to pour tower
base; completion anticipated sometime during 2019.
166. Lisbon Portugal
Temple: Excavation underway for temple; structural framing going up for
meetinghouse; completion anticipated sometime during 2019.
Construction pending:
167. Winnipeg Manitoba
Temple: Groundbreaking held Saturday December 3, 2016; awaiting
full-scale operations; if construction commences in April or May, it could be
completed somewhere around early 2019.
Groundbreaking Scheduled:
168. Rio de Janeiro Brazil Temple:
Preparing for groundbreaking; environmental license issued in November 2016;
groundbreaking scheduled for Saturday
March 4, 2017; taking into account any delays, it
seems safe to say that construction there might be completed around late 2019.
169.
Arequipa Peru Temple: Preparing for groundbreaking; erecting construction
barrier; clearing and leveling site; groundbreaking scheduled for Saturday March 4, 2017; given what is known about how quickly construction might
progress, it seems safe to say that construction will be completed sometime
around late 2019.
Rededication Scheduled:
8. Idaho Falls Idaho
Temple: Closed for renovation; finish work underway; rededication scheduled for
Sunday June 4, 2017.
Undergoing Renovation:
20. Jordan River Utah
Temple: Closed for renovation; rededication anticipated sometime between early-and-mid
2018.
41. Frankfurt Germany
Temple: Closed for renovation; some exterior stone removed; foundation exposed;
old meetinghouse razed; rededication anticipated sometime between early-and
mid-2018.
Renovation Scheduled:
13. Oakland California Temple:
Scheduled to close for renovation in February 2018; renovation may be completed
around mid-to-late 2019.
Announced:
170. Harare Zimbabwe
Temple: Approval and construction preparation phase; site announcement
anticipated sometime later this year, with a
groundbreaking to take place a short time after the site announcement. (This is
according to a report from a Church leader in the area.)
171. Port-au-Prince
Haiti Temple: Planning and design phase; awaiting official site announcement. NOTE:
According to member reports, a potential site has been identified but has yet
to be confirmed.
172. Bangkok Thailand
Temple: Planning phase; awaiting official site announcement. NOTE: Some reports
have indicated that a Church office building may be redesigned and renovated as
a multi-purpose building that will not only continue to house Church offices
but also a meetinghouse in addition to a temple.
173. Lima Peru Los
Olivos Temple: Planning phase; awaiting official site announcement. NOTE: Even
though this was the last of the four temples that was announced most recently,
and in spite of the fact that an official site has not yet been announced, the
announced name for this second temple in Lima seems to indicate that it will be
constructed somewhere in the Los Olivos District. For that reason, it seems
appropriate to put this temple ahead of the others.
174. Abidjan Ivory
Coast Temple: Planning phase; awaiting official site announcement.
175. Quito Ecuador
Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil
Temple: Planning phase; awaiting official site announcement.
177. Urdaneta
Philippines Temple: Stalled in planning and approval phase; awaiting
official site announcement. NOTE: Even though this temple is technically ahead
of the temples listed above in terms of its status, because it is unclear why
progress has been stalled or how long those delays might last, we could see any
or all of the temples above have their constructions commence before anything
gets resolved with this one.
Key:
Bolded numbers and text denote
temples whose numbers already exists (for renovations), or is certain due to a
scheduled dedication, as well as information that is certain, such as
dedication or groundbreaking dates.
Italicized numbers and
text denote temples whose numbers may change based on the order in
which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote
temples whose numbers may change based on progress towards planning, approval,
and groundbreaking.
Red text denotes changes from
the last posted temple progress report.