Temple Construction Progress Report
(current as of 12/15/16)
Current Temple Status: 155 operating; 1 scheduled
for dedication; 11 under construction; 1 scheduled for rededication; 2
undergoing renovation; 10 announced;
(NOTE: Up to 3
additional temples may soon have a groundbreaking announced).
Dedication scheduled:
156. Paris
France Temple: Interior work underway; open house and dedication dates
announced; scheduled to be dedicated on Sunday
May 21, 2017.
Under Construction:
157. Meridian Idaho
Temple: Exterior lighting tests underway; welcome center reopens in stake
center; completion anticipated sometime in late 2017.
158. Cedar City Utah
Temple: Fencing progressing;
entrance plaza created; garden and natural landscaping areas defined; completion anticipated sometime
in late 2017.
159. Tucson Arizona
Temple: Pouring walkways; erecting fencing; installing
art glass windows; completion anticipated sometime in late 2017.
160. Rome Italy Temple:
Interior work progressing; completion
anticipated sometime in 2018.
161. Concepcion Chile
Temple: Attaching building wrap to exterior walls;
adding landscaping structures; completion anticipated sometime in 2018.
162. Kinshasa Democratic
Republic of the Congo Temple: Building
the exterior walls; completion anticipated sometime in 2018.
163.
Durban South Africa Temple: Pouring temple foundation; setting rebar for
missionary housing walls; palm trees planted along entrance road; completion
anticipated sometime in 2018.
164. Barranquilla
Colombia Temple: Exterior walls rising; completion anticipated sometime between 2018 and 2019.
165.
Winnipeg Manitoba Temple: Groundbreaking held Saturday December 3, 2016;
completion anticipated sometime between 2018
and 2019.
166.
Fortaleza Brazil Temple: Concrete
forms going up for second floor exterior walls; completion
anticipated sometime in 2019.
167. Lisbon Portugal Temple:
Laying meetinghouse footings and foundation; excavating for maintenance
building; temple site cleared; completion anticipated sometime in 2019.
Scheduled for rededication:
8. Idaho Falls Idaho
Temple: Closed for renovation; finish work underway; rededication scheduled for
Sunday June 4, 2017.
Undergoing Renovation:
20. Jordan River Utah
Temple: Closed for renovation; rededication anticipated sometime between late
2017 and early 2018.
41. Frankfurt Germany
Temple: Closed for renovation; some exterior stone removed; foundation exposed;
old meetinghouse razed; rededication anticipated sometime in 2018.
Announced:
168.
Harare Zimbabwe Temple: Approval and construction preparation phase;
official site announcement anticipated in early 2017, with the groundbreaking
anticipated to take place shortly following the site announcement.
169. Rio de Janeiro
Brazil Temple: Governmental approval phase; preliminary environmental license
issued in November 2016; groundbreaking pending.
170. Arequipa Peru Temple:
General contractor selected; groundbreaking pending.
171. Urdaneta
Philippines Temple: Planning and approval phase; awaiting official site
announcement.
172. Port-au-Prince
Haiti Temple: Planning and approval phase; awaiting official site announcement.
173. Bangkok Thailand
Temple: Planning and approval phase; awaiting official site announcement.
174. Abidjan Ivory
Coast Temple: Planning phase; awaiting official site announcement.
175. Quito Ecuador
Temple: Planning phase; awaiting official site announcement.
176. Belem Brazil
Temple: Planning phase; awaiting official site announcement.
177. Lima Peru Los
Olivos Temple: Planning phase; awaiting official site announcement.
Key:
Bolded numbers and text denote
temples whose numbers already exists (for renovations), or is certain due to a
scheduled dedication, as well as information that is certain, such as dedication
or groundbreaking dates.
Italicized numbers and
text denote temples whose numbers may change based on the order in
which future dedications and groundbreakings are scheduled.
Underlined numbers and text denote
temples whose numbers may change based on progress towards planning, approval,
and groundbreaking.
Red text denotes
changes from the last posted temple progress update.